One Bridge Out, One To Go

The Highlights

  • Merchants Row:  Temporary bridge removed, street now closed to thru traffic

  • Main Street:  Normal two-lane traffic resumes next week

  • Pedestrian Alert:  Main Street footbridge and Printer’s Alley reopen, Merchants Row...

Pace Picks Up in Downtown Construction

The Highlights

  • Merchants Row to close to thru traffic for the summer starting Tuesday

  • Merchants Row Bridge to be removed on Thursday

  • Main Street again reduced to one lane downtown next week

  • Pedestrian Alert:  Foot...

Middlebury Project Gets Full Go-Ahead

Last week came to a close with some good news.

Friday afternoon VTrans informed Town leadership and Kubricky that restrictions on the number of workers allowed on site had been eased to the point where Kubricky can now field a full c...

Back At Work, Downtown Drilling Takes Center Stage

The Highlights

  • Merchants Row closed to thru traffic Friday and Monday

  • Saturday work schedule

  • Main Street reduced to one lane downtown next two weeks

After a pause of nearly seven weeks, the sights and sou...

Work To Resume on Monday

It’s been a busy week following VTrans getting the go-ahead to resume work on Middlebury’s downtown construction project.

Much of the focus this week has been on working out the logistics of restarting construction in accordance with our new real...

It's Back to Work!

Here’s the news we’ve been waiting for.

Late on Friday we heard from VTrans that Middlebury's rail and bridge project has been given the green light to restart construction this week.

Ours is the only construction project in Vermont with out-of-state wo...

Please reload

Recent Posts

October 22, 2020

October 8, 2020

October 1, 2020

September 24, 2020

September 17, 2020

September 15, 2020

September 10, 2020

September 3, 2020

August 27, 2020

August 20, 2020

Please reload

Archive
Please reload

© 2016 byTown of Middlebury,  All rights reserved.. Proudly created with Wix.com