10-Week Closure of Main Street Gets Underway

The Highlights

  • Main Street temporary bridge now gone

  • Construction of downtown tunnel begins next week

  • Left-hand turn from South Pleasant Street onto Cross Street temporarily eliminated

Right on schedule, the 10...

10-Week Closure of Main Street Begins Monday

The Highlights

  • Following up on Wednesday’s Public Meeting

  • What’s happening Week 1

  • Eat Local, Win Money

Wednesday night, on the eve of the main phase of Middlebury’s Downtown Rail & Bridge Project, VTrans, VHB a...

Where to Park Downtown Starting Next Week

The Highlights

  • Where to park during the 10-week closure of Main Street

  • Temporary suspension of parking on South Main Street late July – early August

In the past two days we’ve talked about getting around downtown on fo...

What Motorists Can Expect Starting Next Week

The Highlights

  • How the 10-week closure of Main Street will impact motorists and bicyclists

  • Final Reminder to attend Virtual Public Meeting Wednesday, July 8, at 7 PM

Before we look at getting around downtown by car,...

What Pedestrians Can Expect Starting Next Week

The Highlights

  • How the 10-week closure of Main Street will impact sidewalk travel

  • Introducing The Shuttlebury, a free continuous-loop downtown shuttle service

  • Temporary lane closure on Main Street to install wa...

300-Ton Crane’s Arrival Downtown Signals Start of Main Event

The Highlights

  • 10-Week Closure of Main Street begins Monday, July 13

  • Virtual Public Meeting scheduled for 7 PM Wednesday, July 8

  • Temporary lane closure next week on Main Street to install water li...

300-Ton Crane Arrives in Triangle Park Monday

The Highlights

  • Intermittent lane closures on Main Street Monday as crane parts are trucked in

  • Main Street closed overnight on Monday to assemble crane boom in roadway

  • Public Meeting scheduled for Wednesday, July...

Temporary Detour for Motorists

Entering and Exiting the Marble Works

The Highlights

  • Middle Seymour Street closed to thru traffic starting Wednesday 7 AM

  • Traffic to enter and exit the Marble Works from Seymour Street

  • Middle Seymour to reopen each evening at 7...

Cranes for Setting Precast To Start Arriving in Town Next Week

The Highlights

  • 200-ton cranes to be assembled downtown in preparation for tunnel construction

  • Middle Seymour entrance to the Marble Works reduced to one lane next two weeks

  • Upcoming live updates...

Downtown Main Street To Close Briefly Wednesday Morning

The Highlights

  • Kubricky to conduct a trial run of precast from Fifield Farm to central downtown

  • Main Street to close between Cross Street roundabout and Seymour Street 6:30 – 8:30 AM

  • Parking on South M...

Please reload

Recent Posts

September 17, 2020

September 15, 2020

September 10, 2020

September 3, 2020

August 27, 2020

August 20, 2020

August 13, 2020

August 6, 2020

July 30, 2020

July 23, 2020

Please reload

Archive
Please reload

© 2016 byTown of Middlebury,  All rights reserved.. Proudly created with Wix.com