Temporary Bridges Update #32
Tuesday Wrap-Up. Lots of activity in the construction zone today. Kubricky built up the southern approach to the bridge abutment as...


Temporary Bridges Update #31
Monday Wrap-Up. Despite the steady rain, Kubricky executed the day’s construction plan on Main Street. In the morning, Kubricky...


Temporary Bridges Update #30
Friday, July 21, Marks the End for 100-Year-Old Main Street Bridge In just a few short hours on Friday night—and following several years...


Temporary Bridges Update #29
Thursday Wrap-Up: Main Street. As planned, Kubricky closed Main Street between the crosswalk connecting Triangle Park to the National...
Temporary Bridges Update #28
Demolition of Main Street Bridge Begins Today What’s On Tap: Main Street. Early morning, Kubricky uses construction barrels to close...
Temporary Bridges Update #27
Preparing for Thursday’s Closing of Main Street In today’s update, I want to remind everyone that demolition of the Main Street Bridge...
Temporary Bridges Update #26
It’s Our Downtown In today’s update, I’ll focus on the things we’re putting in place to try to minimize the disruption to downtown during...
Temporary Bridges Update #25
Demolition of Downtown Bridges Begins Thursday, July 20 Following the Lion’s Club Auction and Barbeque, which takes place Wednesday, July...
Temporary Bridges Update #24
Down Time in Downtown I hope everyone has been enjoying Festival on the Green this week and that you had an opportunity to take part in...


Temporary Bridges Update #23
A Primer on Our New Temporary Bridges One of the questions I’m asked most frequently is, “So what are these temporary bridges going to...