2020 Update #28
10-Week Shutdown Dates Set The Highlights Construction of downtown tunnel expected to start on or about July 13 Main Street to close...
2020 Community Update #27
Progress, Step by Step The Highlights Construction moves from Main Street back into rail corridor Precast nears half-way point at Fifield...
2020 Update #26
One Bridge Out, One To Go The Highlights Merchants Row: Temporary bridge removed, street now closed to thru traffic Main Street: Normal...
2020 Update #25
Pace Picks Up in Downtown Construction The Highlights Merchants Row to close to thru traffic for the summer starting Tuesday Merchants...
2020 Update #24
Middlebury Project Gets Full Go-Ahead Last week came to a close with some good news. Friday afternoon VTrans informed Town leadership and...
2020 Update #23
Back At Work, Downtown Drilling Takes Center Stage The Highlights Merchants Row closed to thru traffic Friday and Monday Saturday work...
2020 Update #22
Work To Resume on Monday It’s been a busy week following VTrans getting the go-ahead to resume work on Middlebury’s downtown construction...
2020 Update #21
It's Back to Work! Here’s the news we’ve been waiting for. Late on Friday we heard from VTrans that Middlebury's rail and bridge project...
2020 Update #20
Almost There The Governor’s announcement last Friday that outdoor construction crews could expand from two to five people put us on a...
2020 Update #19
Awaiting Friday’s Press Conference, Walking Into History It’s tempting to see Thursday’s marvelously clear blue skies as a harbinger of...